N2 - The vacuum preloading method has been used in a number of countries for soil improvement and land reclamation works. Prefabricated vertical drains are normally used together with the vacuum preloading technique. When a surcharge load larger than the vacuum load is required, a combined vacuum and fill surcharge preloading method is also adopted. The mechanism of the vacuum preloading method is explained by examining the pore water pressure and effective stress changes in both the fill surcharge and vacuum preloading cases. Two case studies are presented to illustrate the applications of the vacuum preloading method and the combined vacuum and fill surcharge preloading method. Discussions on the effective depth of the vacuum preloading method and the methods to estimate the degree of consolidation are also made. Copyright ASCE 2009.
AB - The vacuum preloading method has been used in a number of countries for soil improvement and land reclamation works. Prefabricated vertical drains are normally used together with the vacuum preloading technique. When a surcharge load larger than the vacuum load is required, a combined vacuum and fill surcharge preloading method is also adopted. The mechanism of the vacuum preloading method is explained by examining the pore water pressure and effective stress changes in both the fill surcharge and vacuum preloading cases. Two case studies are presented to illustrate the applications of the vacuum preloading method and the combined vacuum and fill surcharge preloading method. Discussions on the effective depth of the vacuum preloading method and the methods to estimate the degree of consolidation are also made. Copyright ASCE 2009.
UR - http://www.scopus.com/inward/record.url?scp=69949104464&partnerID=8YFLogxK
UR - http://www.scopus.com/inward/citedby.url?scp=69949104464&partnerID=8YFLogxK
U2 - 10.1061/41025(338)33
DO - 10.1061/41025(338)33
M3 - Conference contribution
AN - SCOPUS:69949104464
SN - 9780784410257
T3 - Geotechnical Special Publication
SP - 308
EP - 317
BT - Advances in Ground Improvement
T2 - Advances in Ground Improvement: Research to Practice in the United States and China - 2009 US-China Workshop on Ground Improvement Technologies
Y2 - 14 March 2009 through 14 March 2009
ER -